Planning application number: 22/1442/FUL

Site address

Ham Close, Ham Village Green, Car Park To East Of Ham Village Green, And Part Of Woodville Day Centre Site And St Richards Church Of England Primary School Site, Ham (View Site Plan)

View

Status:

Granted Permission 22/03/2023

Latest: Decision Issued

Level: Committee Decision

Details

Proposal

Demolition of existing buildings on-site and change of use of land within Ham Close, the Woodville Day Centre and St Richards Church of England Primary School and the existing recycling and parking area to the east of Ham Village Green for a phased mixed-use redevelopment comprising: a. 452 residential homes (Class C3) up to 6 storeys (with plant above) b. Community/Leisure Facility (Class F2) of up to 3 storeys in height (with plant above) c. Maker labs (sui generis) of up to 2 storeys d. Basement car park e. Provision of on-site cycle, vehicle and servicing parking f. Provision of amenity space and playspace g. Site wide landscaping and alterations to Ham Village Green, and h. New pedestrian, vehicle and cycle accesses and internal routes and associated highways works

Type

Full Application

Ward

HAM, PETERSHAM, RICHMOND RIVERSIDE WARD

Applicant

Show applicant details

Agent

Mr Jon Turner Kings House 101-135 Kings Road Brentwood CM14 4DR

Officer

Grace Edwards

Site plan

View Site Plan

Progress

A decision has been issued by the authority.

A copy of the decision notice will appear in the case file soon, and within a maximum of two weeks.
  • Application Received: 04/05/2022
  • Validated: 09/06/2022
  • Neighbour notification started: 05/12/2022
  • Neighbour notification ended: 24/07/2022
  • Decision Issued: 22/03/2023

Documents and images

DescriptionReferenceDate Published
Playspace details 2 11265-LD-PLN-212 E23 Sep 2022
Playspace details 3 11265-LD-PLN-213 E23 Sep 2022
Block B Elevations 3 & 4 HCR-BPTW-B02-ZZ-DR-A-2003-C02-A3 -28 Sep 2022
Block N ground floor plan HCR-BPTW-B14-00-DR-A-1140-C03-A328 Sep 2022
Block N ground floor refuse store plan HCR-BPTW-B14-00-DR-A-5908-C03-A328 Sep 2022
Block O Elevations HCR-BPTW-B15-ZZ-DR-A-2015-C02-A3 -28 Sep 2022
Block O ground floor plan HCR-BPTW-B15-00-DR-A-1150-C02-A328 Sep 2022
Block O ground floor refuse store plan HCR-BPTW-B15-00-DR-A-5909-C02-A328 Sep 2022
Block W Elevations 3 & 4 HCR-BPTW-B23-ZZ-DR-A-2022-C01-A3 -28 Sep 2022
Block W first floor plan HCR-BPTW-B23-01-DR-A-1231-C02-A328 Sep 2022
Block W ground floor plan HCR-BPTW-B23-00-DR-A-1230-C02-A328 Sep 2022
Block W roof plan HCR-BPTW-B23-04-DR-A-1234-C02-A328 Sep 2022
Block W second floor plan HCR-BPTW-B23-02-DR-A-1232-C02-A328 Sep 2022
Block W third floor plan HCR-BPTW-B23-03-DR-A-1233-C02-A328 Sep 2022
DETAILED MASTERPLAN FIFTH FLOOR HCR-BPTW-S01-05-DR-A-0125-C02-A328 Sep 2022
DETAILED MASTERPLAN FIRST FLOOR HCR-BPTW-S01-01-DR-A-0121-C02-A328 Sep 2022
DETAILED MASTERPLAN FOURTH FLOOR HCR-BPTW-S01-04-DR-A-0124-C02-A328 Sep 2022
Detailed masterplan ground floor HCR-BPTW-S01-00-DR-A-0120-C02-A328 Sep 2022
DETAILED MASTERPLAN SECOND FLOOR HCR-BPTW-S01-02-DR-A-0122-C02-A328 Sep 2022
Detailed masterplan sixth floor HCR-BPTW-S01-06-DR-A-0126-C02-A328 Sep 2022
DETAILED MASTERPLAN THIRD FLOOR HCR-BPTW-S01-03-DR-A-0123-C02-A328 Sep 2022
Hard landscape general arrangement 1 of 4 11265-LD-PLN-201-P0728 Sep 2022
Hard landscape general arrangement 2 of 4 11265-LD-PLN-202-P0728 Sep 2022
Hard landscape general arrangement 3 of 4 11265-LD-PLN-203-P0928 Sep 2022
Hard landscape general arrangement 4 of 4 11265-LD-PLN-204-P0728 Sep 2022
illustrative masterplan 11265-LD-PLN-10028 Sep 2022
proposed access plan HCR-BPTW-S01-ZZ-DR-A-0107-C02-A328 Sep 2022
proposed accessibility routes HCR-BPTW-S01-ZZ-DR-A-0108-C02-A328 Sep 2022
proposed building heights strategy HCR-BPTW-S01-ZZ-DR-A-0111-C02-A328 Sep 2022
proposed community centre ground floor plan WRAP_GA_A_0166 P0328 Sep 2022
proposed cycle storage strategy HCR-BPTW-S01-ZZ-DR-A-0105-C02-A328 Sep 2022
proposed energy centre and sub stations HCR-BPTW-S01-ZZ-DR-A-0110-C02-A328 Sep 2022
proposed FFLs plan HCR-BPTW-S01-ZZ-DR-A-0113-C02-A328 Sep 2022
proposed fire strategy HCR-BPTW-S01-ZZ-DR-A-0106-C02-A328 Sep 2022
proposed makerslab ground floor plan WRAP_GA_A_0166 P0328 Sep 2022
proposed makerslab ground floor refuse plan WRAP_GA_A_0190 P0228 Sep 2022
proposed masterplan HCR-BPTW-S01-ZZ-DR-A-0102-C02-A328 Sep 2022
proposed masterplan mix HCR-BPTW-S01-ZZ-DR-A-0130-C02-A328 Sep 2022
proposed masterplan tenure HCR-BPTW-S01-ZZ-DR-A-0140-C02-A328 Sep 2022
proposed parking strategy HCR-BPTW-S01-ZZ-DR-A-0109-C02-A328 Sep 2022
proposed phase 1 masterplan HCR-BPTW-S01-ZZ-DR-A-0114-C02-A328 Sep 2022
proposed phase 2 masterplan HCR-BPTW-S01-ZZ-DR-A-0115-C03-A328 Sep 2022
proposed phase 3 masterplan HCR-BPTW-S01-ZZ-DR-A-0116-C03-A328 Sep 2022
proposed phasing plan HCR-BPTW-S01-ZZ-DR-A-0103-C03-A328 Sep 2022
proposed refuse strategy HCR-BPTW-S01-ZZ-DR-A-0104-C03-A328 Sep 2022
proposed roof plan strategy HCR-BPTW-S01-ZZ-DR-A-0112-C02-A328 Sep 2022
site demolition plan HCR-BPTW-S01-ZZ-DR-A-0010-C03-A328 Sep 2022
Soft landscape general arrangement 1 of 4 11265-LD-PLN-401-P0528 Sep 2022
Soft landscape general arrangement 2 of 4 11265-LD-PLN-402-P0528 Sep 2022
Soft landscape general arrangement 3 of 4 11265-LD-PLN-403-P0528 Sep 2022
Soft landscape general arrangement 4 of 4 11265-LD-PLN-404-P0528 Sep 2022
construction phasing plan  27 Oct 2022
Demolition phasing plan  27 Oct 2022