BLOCK B ELEVATIONS 3 & 4
| HCR-BPTW-B02-ZZ-DR-A-2003-C01-A3 - | 10 May 2022 |
BLOCK N - GROUND FLOOR PLAN
| HCR-BPTW-B14-00-DR-A-1140-C01-A3 - | 10 May 2022 |
HARD LANDSCAPE GENERAL ARRANGEMENT (SHEETS 1 OF 4)
| 11265-LD-PLN-201 | 10 May 2022 |
HARD LANDSCAPE GENERAL ARRANGEMENT (SHEETS 2 OF 4)
| 11265-LD-PLN-202 | 10 May 2022 |
HARD LANDSCAPE GENERAL ARRANGEMENT (SHEETS 3 OF 4)
| 11265-LD-PLN-203 | 10 May 2022 |
HARD LANDSCAPE GENERAL ARRANGEMENT (SHEETS 4 OF 4)
| 11265-LD-PLN-204 | 10 May 2022 |
ILLUSTRATIVE MASTERPLAN (SITE WIDE)
| 11265-LD-PLN-100 | 10 May 2022 |
SOFT LANDSCAPE GENERAL ARRANGEMENT (SHEETS 1 OF 4)
| 11265-LD-PLN-401 | 10 May 2022 |
SOFT LANDSCAPE GENERAL ARRANGEMENT (SHEETS 2 OF 4)
| 11265-LD-PLN-402 | 10 May 2022 |
SOFT LANDSCAPE GENERAL ARRANGEMENT (SHEETS 3 OF 4)
| 11265-LD-PLN-403 | 10 May 2022 |
SOFT LANDSCAPE GENERAL ARRANGEMENT (SHEETS 4 OF 4)
| 11265-LD-PLN-404 | 10 May 2022 |
BLOCK O - GROUND FLOOR PLAN
| HCR-BPTW-B15-00-DR-A-1150-C01-A3 - | 11 May 2022 |
BLOCK O ELEVATIONS
| HCR-BPTW-B15-ZZ-DR-A-2015-C01-A3 - | 11 May 2022 |
BLOCK W - FIRST FLOOR PLAN
| HCR-BPTW-B23-01-DR-A-1231-C01-A3 - | 11 May 2022 |
BLOCK W - GROUND FLOOR PLAN
| HCR-BPTW-B23-00-DR-A-1230-C01-A3 - | 11 May 2022 |
BLOCK W - ROOF PLAN
| HCR-BPTW-B23-04-DR-A-1234-C01-A3 - | 11 May 2022 |
BLOCK W - SECOND FLOOR PLAN
| HCR-BPTW-B23-02-DR-A-1232-C01-A3 - | 11 May 2022 |
BLOCK W -THIRD FLOOR PLAN
| HCR-BPTW-B23-03-DR-A-1233-C01-A3 - | 11 May 2022 |
BLOCK W ELEVATIONS 3 & 4
| HCR-BPTW-B23-ZZ-DR-A-2022-C01-A3 - | 11 May 2022 |
DETAILED MASTERPLAN FIFTH FLOOR
| HCR-BPTW-S01-05-DR-A-0125-C01-A3 - | 11 May 2022 |
DETAILED MASTERPLAN FIRST FLOOR
| HCR-BPTW-S01-01-DR-A-0121-C01-A3 - | 11 May 2022 |
DETAILED MASTERPLAN FOURTH FLOOR
| HCR-BPTW-S01-04-DR-A-0124-C01-A3 - | 11 May 2022 |
DETAILED MASTERPLAN GROUND FLOOR
| HCR-BPTW-S01-00-DR-A-0120-C01-A3 - | 11 May 2022 |
DETAILED MASTERPLAN SECOND FLOOR
| HCR-BPTW-S01-02-DR-A-0122-C01-A3 - | 11 May 2022 |
DETAILED MASTERPLAN SIXTH FLOOR
| HCR-BPTW-S01-06-DR-A-0126-C01-A3 - | 11 May 2022 |
DETAILED MASTERPLAN THIRD FLOOR
| HCR-BPTW-S01-03-DR-A-0123-C01-A3 - | 11 May 2022 |
PROPOSED ACCESS PLAN
| HCR-BPTW-S01-ZZ-DR-A-0107-C01-A3 - | 11 May 2022 |
PROPOSED ACCESSIBILITY ROUTES
| HCR-BPTW-S01-ZZ-DR-A-0108-C01-A3 - | 11 May 2022 |
PROPOSED BUILDING HEIGHTS STRATEGY
| HCR-BPTW-S01-ZZ-DR-A-0111-C01-A3 - | 11 May 2022 |
PROPOSED CYCLE STORAGE STRATEGY
| HCR-BPTW-S01-ZZ-DR-A-0105-C01-A3 - | 11 May 2022 |
PROPOSED ENERGY CENTRE & SUB-STATIONS
| HCR-BPTW-S01-ZZ-DR-A-0110-C01-A3 - | 11 May 2022 |
PROPOSED FFLS PLAN
| HCR-BPTW-S01-ZZ-DR-A-0113-C01-A3 - | 11 May 2022 |
PROPOSED FIRE STRATEGY
| HCR-BPTW-S01-ZZ-DR-A-0106-C01-A3 - | 11 May 2022 |
PROPOSED MASTERPLAN
| HCR-BPTW-S01-ZZ-DR-A-0102-C01-A3 - | 11 May 2022 |
PROPOSED MASTERPLAN MIX
| HCR-BPTW-S01-ZZ-DR-A-0130-C01-A3 - | 11 May 2022 |
PROPOSED MASTERPLAN TENURE
| HCR-BPTW-S01-ZZ-DR-A-0130-C01-A3 - | 11 May 2022 |
PROPOSED PARKING STRATEGY
| HCR-BPTW-S01-ZZ-DR-A-0109-C01-A3 - | 11 May 2022 |
PROPOSED PHASE 1 MASTERPLAN
| HCR-BPTW-S01-ZZ-DR-A-0114-C01-A3 - | 11 May 2022 |
PROPOSED PHASE 2 MASTERPLAN
| HCR-BPTW-S01-ZZ-DR-A-0115-C01-A3 - | 11 May 2022 |
PROPOSED PHASE 3 MASTERPLAN
| HCR-BPTW-S01-ZZ-DR-A-0116-C01-A3 - | 11 May 2022 |
PROPOSED PHASING PLAN
| HCR-BPTW-S01-ZZ-DR-A-0103-C01-A3 - | 11 May 2022 |
PROPOSED REFUSE STRATEGY
| HCR-BPTW-S01-ZZ-DR-A-0104-C01-A3 - | 11 May 2022 |
PROPOSED ROOF PLAN STRATEGY
| HCR-BPTW-S01-ZZ-DR-A-0112-C01-A3 - | 11 May 2022 |
SITE DEMOLITION PLAN
| HCR-BPTW-SE-ZZ-DR-A-0010-C01-A3 - | 11 May 2022 |
BLOCK N GROUND FLOOR REFUSE STORE PLAN
| HCR-BPTW-B14-00-DR-A-5908-C01-A3 | 13 Jun 2022 |
BLOCK O GROUND FLOOR REFUSE STORE PLAN
| HCR-BPTW-B15-00-DR-A-5909-C01-A3 | 13 Jun 2022 |
PLAY SPACE DETAIL PLANS
| 11265-LD-PLN-211 B | 13 Jun 2022 |
PLAY SPACE DETAIL PLANS
| 11265-LD-PLN-212 B | 13 Jun 2022 |
PLAY SPACE DETAIL PLANS
| 11265-LD-PLN-213 B | 13 Jun 2022 |
PROPOSED GROUND FLOOR PLAN
| WRAP_GA_A_0166 P02 | 13 Jun 2022 |
PROPOSED GROUND FLOOR REFUSE STRATEGY PLAN
| WRAP_GA_A_190 P01 | 13 Jun 2022 |
PROPOSED GROUND FLOOR STRATEGY PLAN
| WRAP_GA_A_190 P01 | 13 Jun 2022 |
PROPOSED REFUSE STRATEGY
| HCR-BPTW-S01-ZZ-DR-A-0104-C02-A3 | 13 Jun 2022 |
PROPOSED GROUND FLOOR PLAN
| WRAP_GA_A_0166 P02 | 14 Jun 2022 |