Proposal

Erection of a new four-storey block (Block A), comprising of a ground-floor café (Use class E(b)), with the upper floor in office use (Class E(g)(i) at the front corner of St Margarets Road and The Barons, together with the partial demolition of Block C and the construction of a single storey extension, the construction of an additional storey and external stair access to Block E, the construction of an additional storey above Block H and the refurbishment and modernisation of all existing blocks within the site along with new signage

Type

Full Application

Ward

ST MARGARETS, NORTH TWICKENHAM WARD - Historic From 06/05/20

Applicant

Show applicant details

Agent

Mark Batchelor 2nd Floor, 24 Southwark Bridge Road London SE1 9HF

Officer

Andrew Vaughan

Site plan

View Site Plan

Progress

A decision has been issued by the authority.

A copy of the decision notice will appear in the case file soon, and within a maximum of two weeks.
  • Application Received: 12/01/2021
  • Validated: 14/01/2021
  • Neighbour notification started: 18/10/2021
  • Neighbour notification ended: 05/03/2021
  • Decision Issued: 14/01/2022

Documents and images

DescriptionDate Published
(SUPERSEEDED) SUSTAINABILITY STATEMENT 12 Jan 2021
Air Quality Assessment 12 Jan 2021
Arboricultural Impact Assessment and Method Statement 12 Jan 2021
Bat Method Statement 12 Jan 2021
CIL Schedule Qn.7 12 Jan 2021
Daylight and Sunlight 12 Jan 2021
Design and Access Statement - contents 12 Jan 2021
Design and Access Statement - part 1 12 Jan 2021
Design and Access Statement - part 10.1 12 Jan 2021
Design and Access Statement - part 10.2 12 Jan 2021
Design and Access Statement - part 11 12 Jan 2021
Design and Access Statement - part 12 12 Jan 2021
Design and Access Statement - part 13 12 Jan 2021
Design and Access Statement - part 2 12 Jan 2021
Design and Access Statement - part 3 12 Jan 2021
Design and Access Statement - part 4 12 Jan 2021
Design and Access Statement - part 5 12 Jan 2021
Design and Access Statement - part 6 12 Jan 2021
Design and Access Statement - part 7 12 Jan 2021
Design and Access Statement - part 8 12 Jan 2021
Design and Access Statement - part 9.1 12 Jan 2021
Design and Access Statement - part 9.2 12 Jan 2021
Energy Statement 12 Jan 2021
Flood Risk Assessment and Drainage Strategy 1 12 Jan 2021
Flood Risk Assessment and Drainage Strategy 2 12 Jan 2021
Health Impact Assessment 12 Jan 2021
Heritage Statement 12 Jan 2021
Initial Biodiversity Impact Assessment 12 Jan 2021
Noise Assessment 12 Jan 2021
Planning Statement 12 Jan 2021
Preliminary Ecological Appraisal 12 Jan 2021
Sustainable Construction Checklist 12 Jan 2021
Transport Assessment 12 Jan 2021
Travel Plan 12 Jan 2021
Tree Survey 12 Jan 2021
Twickenham Studios - Schedule_RevA 12 Jan 2021
Cavat Assessment 24 May 2021
CAVAT Report 24 May 2021
Fire Statement 24 May 2021
Fire Statemnt 24 May 2021
Bat Method Statement 25 May 2021
BAT ACTIVITY SURVEY REPORT 28 Sep 2021
Members Briefing 21 Oct 2021
ENERGY STATEMENT 28 Oct 2021