Planning application number: 17/4213/FUL

Site address

1, 1A, 1B And 1C King Street; 2-4 Water Lane; The Site Of The Remaining Former Swimming Pool Building At Corner Of Water Lane And The Embankment; And River Facing Parcel Of Land On The Embankment In Front Of Jubilee Gardens, Twickenham (View Site Plan)

View

Status:

Withdrawn by the Applicant 19/06/2018

Latest: Decision Issued

Level: Committee Decision

Details

Proposal

Full planning application for the demolition and removal of all existing buildings and structures and redevelopment with a mixed use development of the site at 1, 1A, 1B and 1C King Street and 2/4 Water Lane; the site of the remaining former swimming pool buildings at the corner of Water Lane and The Embankment; and the river facing parcel of land on The Embankment in front of Diamond Jubilee Gardens. The development proposals comprise: Two 3-4 storey buildings with a partial lower ground floor and a raised walkway to link the two buildings; three seasonal units (201m2) at Lower Ground Floor level; 505m2 A3 floor space, 250m2 B1 floor space, 244m2 A1 floor space and 62m2 flexible commercial at ground floor level (either A1/A3/D1); 39 residential apartments at first, second and third floors (18 no. 1 bedroom, 19 no. 2 bedroom and 2 no. 3 bedroom, including six no. affordable homes) and raised roof terrace; new public square / areas of public realm throughout the site; a Lower Ground Floor car park with new vehicular access from The Embankment consisting of 23 car parking spaces and cycle storage; reconfiguration of street parking in the roads immediately adjacent to the Site and associated highway / footway works; amended pedestrian access and landscaping to the South of Diamond Jubilee Gardens; and amendment of service vehicle access to the service road at the rear of Diamond Jubilee Gardens.

Type

Full Application

Ward

Not known

Applicant

Show applicant details

Agent

Mr Sam Sykes Brooklyn Chambers 11 Goring Road Worthing BN12 4AP

Officer

Lucy Thatcher

Site plan

View Site Plan

Progress

A decision has been issued by the authority.

A copy of the decision notice will appear in the case file soon, and within a maximum of two weeks.
  • Application Received: 27/11/2017
  • Validated: 06/12/2017
  • Neighbour notification started: 26/02/2018
  • Neighbour notification ended: 01/03/2018
  • Decision Issued: 19/06/2018

Documents and images

DescriptionDate Published
ACCOMMODATION SCHEDULE 27 Nov 2017
AIR QUALITY AND ODOUR ASSESSMENT 27 Nov 2017
APPENDIX A ATTRIBUTE RESUTS 27 Nov 2017
Appendix A Attricute Resluts Project 2 27 Nov 2017
APPENDIX A PTAL REPORT 27 Nov 2017
APPENDIX C CPZ MAP 27 Nov 2017
APPENDIX C CPZ ZONE 27 Nov 2017
APPENDIX D PARKING SURVEY METHODOLOGY 27 Nov 2017
ARBORICULTURAL IMPACT ANALYSIS 27 Nov 2017
ARBORICULTURAL METHOD STATEMENT (DRAFT) 27 Nov 2017
ARCHAEOLOGY AND HERITAGE ASSESSMENT 27 Nov 2017
BREEAM 27 Nov 2017
CONSTRUCTION MANAGEMENT PLAN 27 Nov 2017
Daylight and Sunlight Study (Neighbouring Properties) Page 1-21 27 Nov 2017
DAYLIGHT AND SUNLIGHT STUDY (NEIGHBOURING PROPERTIES) PAGE 22-27 27 Nov 2017
DAYLIGHT AND SUNLIGHT STUDY (NEIGHBOURING PROPERTIES) PAGE 28-68 27 Nov 2017
DAYLIGHT AND SUNLIGHT STUDY WITHIN DEVELOPMENT 27 Nov 2017
DELIVERY AND SERVICING PLAN 27 Nov 2017
DESK STUDY AND GROUND INVESTIGATION PLAN 27 Nov 2017
ENVIRONMENTAL NOISE SURVEY AND MECHANICAL PLANT ASSESSMENT 27 Nov 2017
FACADE SOUND INSULATION TARGET INTERNAL NOISE LEVELS 27 Nov 2017
FRAMEWORK COMMERCIAL TRAVEL PLAN 27 Nov 2017
Health Impact Assessment 27 Nov 2017
INCLUSIVE ACCESS STATEMENT 27 Nov 2017
PRELIMINARY ECOLOGICAL APPRAISAL 27 Nov 2017
PRELIMINARY ROOST ASSESSMENT 27 Nov 2017
RESIDENTIAL TRAVEL PLAN 27 Nov 2017
SITE WASTE MANAGEMENT FRAMEWORK 27 Nov 2017
STATEMENT OF COMMUNITY INVOLVEMENT 27 Nov 2017
TRANSPORT ASSESSMENT 27 Nov 2017
TWICKENHAM REDISCOVERED - RIVERSIDE PROJECT ENERGY STRATEGY REPORT - PART 1 OF 2 27 Nov 2017
TWICKENHAM REDISCOVERED - RIVERSIDE PROJECT ENERGY STRATEGY REPORT - PART 2 OF 2 27 Nov 2017
TWICKENHAM REDISCOVERED PROGRAMME RIVERSIDE - UTILITIES STATEMENT 27 Nov 2017
TWICKENHAM RIVERSIDE ISS 2 PT 2 27 Nov 2017
TWICKENHAM RIVERSIDE ISS 2 PT 3 27 Nov 2017
TWICKENHAM RIVERSIDE ISS 2 PT 4 27 Nov 2017
TWICKENHAM RIVERSIDE ISS 2 PT 5 27 Nov 2017
TWICKENHAM RIVERSIDE ISS 2 PT 6 27 Nov 2017
Flood Risk Assessment - Part 1 04 Dec 2017
Flood Risk Assessment - Part 2 04 Dec 2017
Flood Risk Assessment - Part 3 04 Dec 2017
Flood Risk Assessment - Part 4 04 Dec 2017
Flood Risk Assessment - Part 5 04 Dec 2017
Viability Assessment 06 Dec 2017
Viability Assessment - appendix 1 06 Dec 2017
Viability Assessment - appendix 2 06 Dec 2017
Viability Assessment - appendix 3 06 Dec 2017
Viability Assessment - appendix 4 06 Dec 2017
Viability Assessment - appendix 6 06 Dec 2017
Viability Assessment - appendix 7 06 Dec 2017
Brochure - Cycle Works 08 Feb 2018
Construction Management Plan Rev D 08 Feb 2018
Drawing Issue Sheet 08 Feb 2018
Ecology Report 08 Feb 2018
Review of Scheme against Twickenham Area Action Plan Aspirations 08 Feb 2018
Analysis Report tree removal 05 Mar 2018